ICRTec 350kW Gas Turbine Genset
View All Projects

ICRTec 350kW Gas Turbine Genset For Stationary Power

8 Engines developed over 9 Year Program

  • First microturbine with ceramic hot section
  • 1100C/2000F firing temp.
  • Dual-fuel diesel & natural gas
  • Series A milestone
  • 39% shaft efficiency
  • Ultra-low emissions
  • Demo’d transients
  • Product cost validation
  • Kenworth/CEC driving trials
  • NOx < 0.01 g/bhp-hr
  • CO < 0.02 g/bhp-hr
  • Data center / fast transient
  • Target 44% shaft efficiency
  • Series hybrid truck demo
5th Generation Engine For ICR Turbine Engine Company

Two field test units for NRG and Microsoft

  • Standard synchronous generator output for install convenience
  • Upgraded pre-production castings and tooling
  • Ceramic static and rotating hardware implements in High Pressure spool

Performance Targets:

  • 700 kWe (2 x350 kWe)
  • 40+ % efficiency LHVe
  • CARB qualified emissions
  • ISO 8528 transient response qual testing

Power delivery options: Both solutions for powergen applications

Standard 1800 RPM synchronous generator, with gearbox and isolation coupling.

Ultra compact Permeant magnet Alternator (75,000 RPM, 350 kWe)